Last updated 2026-07-11

TL;DR
OSHA's steel erection standard at 29 CFR 1926.750 through 1926.761 (Subpart R) requires contractors to have a written fall protection plan, controlled decking zone procedures, and connector procedures before work starts. Fall protection is required above 15 feet for most steel workers. Connectors get discretion between 15 and 30 feet. Above 30 feet, use is mandatory. Every document has to be site-specific.
What OSHA standard governs steel erection safety?
Steel erection in construction runs under 29 CFR 1926 Subpart R, which OSHA finalized in 2001 after years of negotiation through the Steel Erection Negotiated Rulemaking Advisory Committee (SENRAC). The standard covers 29 CFR 1926.750 through 1926.761 and reaches structural steel assembly, joists, decking, and every hoisting operation tied to them on a construction site.
This is not the general industry standard. If your crew is erecting structural steel frames, setting open web steel joists, or laying metal decking on a construction project, Subpart R applies to you. The general construction fall protection rules at 29 CFR 1926.502 still fill in gaps where Subpart R stays silent, but Subpart R wins where the two overlap.[1]
When OSHA promulgated the rule, it estimated Subpart R would prevent roughly 30 fatalities and 1,142 injuries a year. Whether that estimate held up is hard to verify on its own, but steel erection keeps showing up in OSHA's high-hazard operations, and the OSHA fatality data for construction backs that up.
Subcontract your steel erection? You still have skin in this. The controlling contractor carries specific duties under 29 CFR 1926.752 to hand the steel erector certain written information before anyone sets a column.
What written programs does OSHA actually require for steel erection?
Subpart R requires three kinds of written documentation, and each one has to be site-specific. A generic template you download and never open is not compliant.
1. Site-specific erection plan (29 CFR 1926.752(e)) Before steel erection begins, the controlling contractor gives the steel erector written notice of the concrete or steel conditions that affect erection. Under 29 CFR 1926.752(e), a site-specific erection plan gets developed when the project engineer or the steel erection contractor decides one is needed based on the complexity of the structure or site conditions. On most commercial and industrial projects, a written erection plan is the norm even when the literal text doesn't force it.
2. Written fall protection plan (29 CFR 1926.502(k)) When an employer uses a written fall protection plan instead of conventional fall protection like guardrails or personal fall arrest systems, that plan has to be written, site-specific, and developed under the supervision of a qualified person. It must address each location where conventional protection is infeasible or creates a greater hazard. A blanket statement fails. Name the specific spots, the specific reasons guardrails or nets won't work, and the alternative measures in place.[2]
3. Controlled decking zone (CDZ) procedures (29 CFR 1926.760(c)) Use a controlled decking zone instead of fall protection while installing metal decking, and you need written procedures spelling out the CDZ boundaries (90 feet wide, 200 feet long at most), how many workers can be inside, and how the boundaries are marked. Site-specific, kept at the jobsite.
There is no OSHA form for any of these. You write them, or you use a program generator that asks the right questions site by site. SafetyFolio's program builder walks you through each Subpart R requirement so the output is specific to your project, not a cut-and-paste file a compliance officer sees through in four minutes.
Three more procedures need to live in writing somewhere, even if not as standalone documents: multiple lift rigging (Christmas treeing), column anchor bolt repair, and connector fall protection.
What are the fall protection height thresholds in steel erection?
Steel erection sets a 15-foot fall protection threshold for most workers, not the 6 feet used elsewhere in construction. This is where Subpart R breaks from the standard rules, and it trips people up constantly.
General construction requires fall protection at 6 feet under 29 CFR 1926.502. Steel erection uses higher thresholds because of how the work happens.
| Worker Category | Fall Protection Threshold | Standard |
|---|---|---|
| Connectors (connecting structural members) | 15 feet above lower level | 29 CFR 1926.760(b)(1) |
| Ironworkers in controlled decking zones | 30 feet | 29 CFR 1926.760(c) |
| All other steel erection workers | 15 feet | 29 CFR 1926.760(a) |
| Workers on joists and joist girders | 15 feet | 29 CFR 1926.757(a)(10) |
Connectors get a special provision under 29 CFR 1926.760(b). They must be provided fall protection and trained on it, and between 15 and 30 feet they can choose not to use it. Above 30 feet, use is mandatory with no exception.[3]
Don't misread that as a loophole. The employer still buys the equipment and runs the training. The worker's choice not to clip in between 15 and 30 feet is the worker's right under the standard. The employer's duty to provide, offer, and train is not optional.
Inside a CDZ, the 30-foot threshold only applies within the CDZ boundaries and only while decking is being installed. Step outside the zone or finish the decking phase, and the 15-foot rule snaps back.
This is why your written fall protection plan has to be granular about where each worker stands and which phase of erection they're in. A single line that says "fall protection required above 15 feet" undersells the connector provision and will confuse your crew.
What information must the controlling contractor provide in writing before steel erection starts?
29 CFR 1926.752(a) through (d) puts specific pre-construction disclosure duties on the controlling contractor, and they have to be in writing. They aren't optional even if the steel erector never asks.
The controlling contractor must give the steel erection contractor written notice of:
- Concrete or masonry curing status for footings, piers, and walls (29 CFR 1926.752(a)). The concrete must reach the compressive strength set in the written curing statement before steel goes up. That statement is a required document.
- Approval of the anchor bolt repair procedure (29 CFR 1926.752(d)). If anchor bolts are bent, broken, or out of alignment, the controlling contractor must approve a written procedure from a licensed professional engineer before the steel erector touches them.
- Site layout and conditions (29 CFR 1926.752(c)). Roads, planned storage areas, and overhead obstacles that affect erection have to be communicated in writing.
In practice, a lot of controlling contractors hand this off verbally or assume the erector already knows the site. That assumption writes citations. OSHA inspectors ask for the written concrete curing statement often, and when it doesn't exist, the citation lands on the controlling contractor more than the steel erector.[4]
Running a steel erection sub as a general contractor? Build a pre-erection checklist that captures each item as a signed, dated document. It takes less time than one OSHA citation and far less than one worker injury.
What does a compliant fall protection plan for steel erection actually contain?
A compliant plan under 29 CFR 1926.502(k) names the exact locations where conventional fall protection fails, the alternative measures, and the qualified person responsible. Generic language gets rejected. The plan must include:
1. The specific location or type of work where conventional fall protection is infeasible or creates a greater hazard. 2. A description of the alternative measures used. 3. A description of how those alternative measures get implemented. 4. The name of the qualified person responsible for the plan. 5. Identification of who the plan covers.
The plan stays at the jobsite, available for inspection. If your plan lists "structural steel work" as the location, it will not survive OSHA review. You need something like: "column connection work on gridlines A through D, floors 3 through 7, where the column geometry makes a safety net impractical and a PFAS (personal fall arrest system) anchor is unavailable until the upper chord of the joist is installed."
The qualified person who develops or oversees the plan needs the training required under 29 CFR 1926.761. That's a higher bar than a competent person. A qualified person holds a recognized degree or professional certificate in a relevant field, or has extensive practical experience, and can solve problems specific to the subject matter. For fall protection planning on steel, that usually means a structural engineer or a seasoned ironwork supervisor with documented fall protection credentials.
The plan must be updated whenever conditions change under 1926.502(k)(3)(i). Move to a new section of the building or watch site conditions shift, and you revise. A revision log inside the document makes audit review fast.
Want OSHA's reasoning in its own words? The Subpart R preamble, published in the Federal Register on January 18, 2001, walks through why connectors get the 15-to-30-foot discretion and which alternative measures the agency accepted during rulemaking. Dry reading, but it's the clearest statement of OSHA's intent.[12]
What training does OSHA require for steel erection workers?
29 CFR 1926.761 requires a qualified person to train every worker exposed to fall hazards in steel erection, before that worker is exposed. The standard names who trains and what it covers. Training must address:
- Recognition and identification of fall hazards in the worker's area
- The procedures the employer put in place to control those hazards
- The correct procedures for erecting, maintaining, disassembling, and inspecting the fall protection systems in use
- The limits of those systems
A qualified person delivers it, and it happens before exposure. OSHA sets no minimum hours, but the standard says training must be given in a manner the worker understands, which matters for workers whose first language isn't English.
Retraining kicks in when a worker shows inadequate understanding or the employer has reason to believe the earlier training no longer covers the hazards. Section 1926.761(c) puts that judgment call on the employer.
Worth knowing: Subpart R training is separate from general construction OSHA training. A worker holding an OSHA 30 card has finished a broad orientation, but that card does not satisfy the Subpart R qualified-person training for whoever develops the fall protection plan. The 30-hour course is a solid baseline for supervisors. It is not a substitute for task-specific steel erection training.[5]
Keep written records of who was trained, when, by whom, and what got covered. OSHA doesn't explicitly require written training records under 1926.761, but after an incident, no documentation means the presumption is that training never happened. A sign-in sheet with the trainer's name and the topics is enough.
For supervisors, an OSHA 30 training course backs up site-specific training. It builds the regulatory literacy that helps foremen catch violations before they turn into injuries or citations.
What are the most common OSHA citations in steel erection?
The most common Subpart R citation is a missing or generic written fall protection plan under 29 CFR 1926.502(k), and it doesn't take an injury to trigger. OSHA publishes top citations each year, and Subpart R violations show up reliably in construction inspections. Based on OSHA citation data and enforcement history, the frequent hits are:
| Violation Type | Standard | Typical Penalty Range |
|---|---|---|
| Failure to have written fall protection plan | 29 CFR 1926.502(k) | $1,190 to $15,625 per violation |
| Connectors not provided with fall protection equipment | 29 CFR 1926.760(b) | $1,190 to $15,625 |
| No written concrete curing statement | 29 CFR 1926.752(a) | $1,190 to $15,625 |
| Inadequate perimeter safety cables | 29 CFR 1926.760(a)(2) | $1,190 to $15,625 |
| Multiple lift rigging (Christmas tree) violations | 29 CFR 1926.753(e) | $1,190 to $15,625 |
| Willful or repeat violations | Any Subpart R provision | Up to $156,259 per violation |
Penalty ranges reflect OSHA's 2024 maximum adjustments.[6]
The paperwork violations sting because no one has to get hurt. An inspector who arrives on a scheduled or complaint-driven visit asks for your written fall protection plan before ever walking the field. No plan, and you've picked up a citation before anyone laces a boot on the steel.
The multiple lift rigging citation is less about paper and more about procedure. 29 CFR 1926.753(e) caps Christmas tree lifts at five members, requires each member to weigh 2,000 pounds or less, and requires a qualified rigger. Violations here tend toward serious or willful because the hazard is obvious and the limits are exact.[10]
After a fatality, OSHA reviews every document you have. Your written programs aren't only a compliance chore. They're your evidence that you had a plan and followed it.
How does the controlled decking zone (CDZ) work and what must be in writing?
A controlled decking zone lets workers install metal decking without individual fall protection inside a marked area, available under 29 CFR 1926.760(c) when decking goes down on floors or roofs. It only works during initial installation, and it needs a written procedure kept on site.
The requirements are specific:
- Maximum size: 90 feet wide by 200 feet long
- Workers inside must be trained to recognize fall hazards
- The CDZ must be clearly marked with control lines, ropes, wire, or equivalent
- The number of workers inside is limited to those needed for the work
- No more than two employees inside who aren't doing decking work
Here's the catch most employers miss. The CDZ exists only during the initial installation of decking. Once the decking is laid, the zone is gone and conventional fall protection rules take over. A worker who goes back to patch a hole or reposition a sheet is not covered by the CDZ exception.[7]
Your written CDZ procedure should name: 1. The specific floor(s) where the CDZ gets established 2. The physical markers used and how they get set 3. Who is authorized to work inside 4. How workers get told the CDZ phase is over and standard fall protection resumes 5. The competent person responsible for CDZ oversight
Keep the CDZ procedure in your erection plan or as a standalone attachment. When OSHA arrives, a CDZ with no written procedure is a citation waiting to happen.
What are the requirements for steel joists and decking specifically?
Open web steel joists get their own section at 29 CFR 1926.757, detailed enough that they deserve separate attention in your written program. Metal decking follows under 29 CFR 1926.754.
Key joist requirements your written procedures have to reflect:
- The first two joists on each end of a bay must be secured before any worker walks them (29 CFR 1926.757(a)(1))
- Joists spanning 60 feet or less that require bridging must have that bridging installed and anchored before workers walk the top chord
- For joists spanning more than 60 feet, the written erection plan must address the bridging sequence specifically
- A joist or joist girder can't be placed on a wall or column unless the seat is completely attached
For metal decking under 29 CFR 1926.754:
- Shear connectors and other items projecting through the decking can't be left uncovered when not being worked on
- Roof and floor holes and openings get covered or protected as soon as the decking work passes that point
- Wire mesh, exterior plywood, or equivalent must cover holes larger than 12 inches in either dimension
Your written program should include a decking sequence plan: the order of joist installation, when bridging goes in relative to worker access, and who confirms anchoring before the crew walks. It doesn't need to be long. It needs to be specific enough that a new foreman could read it and run the job right.[13]
For tracking and reporting anything that goes wrong during this work, wire your incident report process into the erection program so workers know who to tell and when.
How often do you need to update your steel erection safety program?
OSHA sets no fixed review interval for most Subpart R documents, but several provisions force updates when conditions change. Update the fall protection plan whenever it stops protecting workers, when work moves to a location the plan doesn't cover, or when site conditions make the alternative measures impractical.
Say you wrote the plan for floors 1 through 5. You need an updated plan before work starts on floors 6 through 10 if any conditions differ (per 29 CFR 1926.502(k)(3)(i)).
The concrete curing statement is site- and project-specific. It does not travel from one project to the next.
Most experienced steel erectors review their written programs at the start of each project phase, after any near-miss or incident, and whenever the competent person changes. Annual reviews are common in well-run shops even on ongoing projects, but treat annual as a floor, not a ceiling.
Section 5(a)(1) of the OSH Act, the general duty to keep workplaces free of recognized hazards, effectively requires you to react to new hazard information as it surfaces, even between formal reviews. A near-miss that exposes a gap in your procedures gets fixed that day, not at the next annual cycle.
Small contractors ask whether they need all this for occasional steel work. Yes. Subpart R applies based on the work type, not the employer's size or how often they do it. A contractor who erects steel twice a year carries the same written program obligations as one who does it weekly.
What's the fastest way for a small contractor to get these written programs done?
The documents aren't complicated once you know what goes in them. The work is knowing exactly what OSHA requires, keeping it site-specific, and maintaining it over time.
Have a safety pro on staff or access to an experienced qualified person? Have them draft the site-specific erection plan and the fall protection plan at the start of each project. Budget a couple of hours per project. The concrete curing statement comes from your structural engineer of record, not from you.
No in-house safety expertise? Two reasonable paths. Hire a consultant (roughly $500 to $2,000 for a site-specific Subpart R plan package, depending on complexity), or use a structured digital tool that walks you through each requirement. SafetyFolio's program builder is built around the actual CFR language, so you answer specific questions about your project and get a plan you can hand to an inspector.
What's a waste of money: generic templates that never prompt for site-specific detail. An inspector who reads a fall protection plan identical to every other plan on the market will ask follow-up questions your crew can't answer about your site.
Also worth doing: run your foremen through a structured OSHA 30 hour online course so they understand why the written programs exist, more than what they say. A foreman who gets the regulatory logic keeps the plan current. One who sees it as paperwork lets it rot.
For the lockout tagout and hazard communication programs that ride alongside steel work (equipment maintenance, welding), treat those as separate written programs with their own required elements.
What records do you need to keep and for how long?
Subpart R doesn't set retention periods for most of its documents, but OSHA's general recordkeeping rules and enforcement reality give you clear guidelines. Keep injury and illness records for five years, and keep every Subpart R plan for at least five years as a practical floor.
OSHA's 300 log requirements (29 CFR 1904) apply to steel erection employers with more than 10 employees in most cases. Keep the 300 log, 300A summary, and 301 incident reports for five years.[8]
For your Subpart R documents:
- Written fall protection plans: keep for the project duration plus the OSHA statute of limitations (6 months for most citations, up to 5 years if fraud is alleged). In practice, keep them 5 years.
- Concrete curing statements: keep with the project file.
- CDZ written procedures: keep through the erection phase plus the project file retention period.
- Training records: keep indefinitely, or at minimum for length of employment plus 3 years. State plan states may require longer.
- Rigging inspection records: keep with the project file, 5 years minimum.
If a worker gets hurt on a steel erection project, your written programs turn into litigation documents. Discovery in a construction negligence case can reach back years, and attorneys will demand every written safety document that existed at the time of the incident. Courts have held employers liable even with no OSHA citation when the written program was clearly inadequate or ignored.
Store your written programs somewhere you can reach on site (a job trailer works), backed up digitally. A program you can't produce during an inspection is functionally the same as one you never wrote.
Frequently asked questions
Does OSHA's steel erection standard apply to residential construction?
Generally no. Subpart R (29 CFR 1926.750 to 1926.761) covers structural steel erection in construction, which usually means commercial, industrial, and multi-story projects. Residential work with light-gauge steel framing typically falls under Subpart Q (scaffolding) and the general construction fall protection rules in 29 CFR 1926.502. If structural steel columns and beams are being erected on a residential project, Subpart R likely applies regardless of the building's end use.
What is a 'qualified person' under OSHA's steel erection standard?
Under 29 CFR 1926.751, a qualified person holds a recognized degree, certificate, or professional standing, or has extensive knowledge, training, and experience that demonstrates the ability to solve problems relating to the subject matter. For steel erection fall protection planning, that usually means a licensed professional engineer or an experienced ironwork supervisor with documented credentials. It's a higher bar than a competent person, who only needs the ability to identify hazards.
Can a steel erection subcontractor use the general contractor's fall protection plan?
No. Under 29 CFR 1926.502(k), the fall protection plan must be developed for the specific work and the specific employer doing it. A plan written for the general contractor's own workers doesn't satisfy the steel erection subcontractor's obligation. Each employer performing steel erection work needs its own site-specific written plan, signed off by a qualified person responsible for that employer's operations.
What is 'Christmas tree' rigging and what does OSHA require for it?
Multiple lift rigging, commonly called Christmas tree rigging, hoists more than one structural member at a time using a single crane pick. OSHA permits it under 29 CFR 1926.753(e)(1) only if no more than five members are lifted per pick, each member weighs 2,000 pounds or less, a qualified rigger performs the lift, and the rigging meets specific requirements. Your written program should address when and how multiple lift rigging is authorized on your project.
How does OSHA define a 'connector' for purposes of the fall protection threshold?
29 CFR 1926.751 defines a connector as an employee who works with hoisting equipment to guide structural steel members into position for bolting or welding. Connectors have a specific provision at 29 CFR 1926.760(b): they must be provided and trained on fall protection above 15 feet, but between 15 and 30 feet they may choose not to use it. Above 30 feet, use is mandatory. The employer's duty to provide and train is unconditional regardless of whether the worker clips in.
What happens if anchor bolts are damaged before steel erection starts?
29 CFR 1926.755(b) bars workers from climbing columns with bent, broken, or out-of-position anchor bolts until a repair procedure is approved. That procedure must be in writing and developed by a licensed professional engineer. The controlling contractor must also approve it in writing before the steel erection contractor proceeds. This is a hard stop, not a judgment call. Proceeding without the written approval is a citable violation.
Are there OSHA requirements for the crane or hoisting equipment used in steel erection?
Yes. Hoisting and rigging in steel erection is covered by both 29 CFR 1926.753 (Subpart R) and 29 CFR 1926.1400 (Subpart CC, cranes and derricks in construction). Subpart CC requires crane operators to be certified or qualified, requires pre-use inspections, and mandates assembly and disassembly procedures. Your steel erection program should reference your Subpart CC compliance documents and crane inspection records. The two standards work together, not independently.
Does OSHA require fall protection for workers on top of steel columns?
Yes, with limited exceptions. Workers positioning themselves on steel columns while structural members are being connected are connectors and fall under the 29 CFR 1926.760(b) provision: fall protection required above 15 feet, discretion between 15 and 30 feet. A worker on top of a column who isn't doing connecting work isn't covered by the connector exception and needs conventional fall protection at the applicable threshold. Your written program should distinguish connector activities from other column-top work.
What is the penalty for not having a written fall protection plan for steel erection?
OSHA can cite a missing written fall protection plan under 29 CFR 1926.502(k) as a serious violation, with penalties up to $15,625 per violation under 2024 maximums. If an injury occurs and no written plan existed, the violation is more likely classified as willful, which carries penalties up to $156,259 per violation. The absence of documentation also substantially weakens your defense in any later civil litigation.
Do state plan states have stricter steel erection requirements than federal OSHA?
State plan states must adopt standards at least as effective as federal OSHA and may go further. California's Cal/OSHA (Title 8 CCR) and Washington's L&I have historically kept fall protection requirements that differ in some particulars from federal Subpart R. Always check your specific state's rules. The 29 state plans and two territorial plans are listed at OSHA.gov. If your state runs its own plan, the federal CFR is your floor, not your ceiling.
How many workers are killed in steel erection each year?
OSHA doesn't publish a standalone steel erection fatality count. BLS data for construction fatalities shows falls consistently account for roughly 35 to 40 percent of all construction deaths, and structural steel work sits among the highest-hazard subcategories. Before Subpart R was promulgated in 2001, OSHA's regulatory analysis estimated about 30 annual fatalities tied specifically to structural steel erection. Current rates are believed lower thanks to the standard, but precise current figures aren't broken out separately by BLS.
Can workers refuse to use fall protection between 15 and 30 feet in steel erection?
Only connectors, as defined in 29 CFR 1926.751, have the right to decline fall protection between 15 and 30 feet. That right exists because the SENRAC committee found certain connection work creates a greater hazard when conventional fall protection is used. The employer still must provide the equipment and training. Any worker not performing connector work does not have this option and must use fall protection above the applicable threshold.
What is the SENRAC and why does it matter for understanding Subpart R?
SENRAC stands for Steel Erection Negotiated Rulemaking Advisory Committee. OSHA convened it in the 1990s to develop Subpart R through a consensus process involving steel erectors, ironworker unions, general contractors, and equipment manufacturers. The result, published January 18, 2001 and effective July 18, 2001, tracks industry practice more closely than most OSHA standards. Knowing practitioners negotiated it explains some unusual provisions, like the connector fall protection discretion between 15 and 30 feet.
Do I need a site-specific erection plan on every steel project?
Not always by the literal text. Under 29 CFR 1926.752(e), a site-specific erection plan is required when the project engineer or the steel erection contractor decides one is needed based on the complexity of the structure or site conditions. On most commercial and industrial projects it's the practical norm anyway. When in doubt, write one. A dated, site-specific plan is cheap insurance against a citation and useful evidence after an incident.
Sources
- OSHA, 29 CFR 1926 Subpart R: Steel Erection: Subpart R governs structural steel erection in construction and runs from 29 CFR 1926.750 through 1926.761
- OSHA, 29 CFR 1926.502(k): Fall protection plan: Written fall protection plans must be site-specific, developed under a qualified person, and address each location where conventional fall protection is infeasible
- OSHA, 29 CFR 1926.760: Fall protection: Connectors must be provided fall protection above 15 feet and above 30 feet its use is mandatory; CDZ workers have a 30-foot threshold during decking installation
- OSHA, 29 CFR 1926.752: Site layout, site-specific erection plan, and construction sequence: Controlling contractors must provide written notification of concrete curing status and site conditions before steel erection begins
- OSHA, 29 CFR 1926.761: Training: Steel erection training must be provided by a qualified person before workers are exposed to fall hazards and must cover recognition of fall hazards and the employer's protection procedures
- OSHA, Penalties page: OSHA Civil Penalty Amounts: OSHA's 2024 maximum penalty for serious violations is $15,625 per violation and for willful or repeat violations is $156,259 per violation
- OSHA, 29 CFR 1926.760(c): Controlled decking zone requirements: CDZ dimensions are limited to 90 feet wide by 200 feet long and the exception applies only during initial decking installation
- OSHA, 29 CFR 1904: Recording and Reporting Occupational Injuries and Illnesses: OSHA 300 logs, 300A summaries, and 301 incident reports must be retained for five years
- Bureau of Labor Statistics, Census of Fatal Occupational Injuries: Falls account for roughly 35 to 40 percent of all construction fatalities annually according to BLS CFOI data
- OSHA, 29 CFR 1926.753: Hoisting and rigging: Multiple lift rigging is limited to five structural members per pick, each weighing 2,000 pounds or less, and must be performed by a qualified rigger
- OSHA, 29 CFR 1926.755: Column anchorage: Workers may not climb columns with damaged anchor bolts until a licensed professional engineer has prepared and the controlling contractor has approved a written repair procedure
- Federal Register, Vol. 66 No. 12, January 18, 2001: Steel Erection Final Rule: OSHA estimated the Subpart R final rule would prevent approximately 30 fatalities and 1,142 injuries per year; the rule became effective July 18, 2001
- OSHA, 29 CFR 1926.757: Open web steel joists: The first two joists on each end of a bay must be secured before any worker walks on them; bridging must be installed and anchored before workers walk top chord on joists 60 feet span or less