Last updated 2026-07-10

TL;DR
OSHA's temporary wiring standard for construction is 29 CFR 1926.405(a)(2), working alongside 1926.404. Together they require GFCI protection on all 120-volt, 15- and 20-amp receptacle outlets (or a written grounding program), hard-service cords, strain relief, weatherproof covers, and daily inspection. Missing GFCI is the most-cited electrical violation on jobsites, with serious penalties reaching $16,131 per violation in 2024.
What OSHA standards cover temporary wiring on construction sites?
The core rule is 29 CFR 1926.405(a)(2), which lives inside Subpart K (Electrical) of OSHA's construction standards. [1] That subpart covers installation safety requirements, and 1926.405 addresses wiring methods, components, and equipment for general use, including the temporary setups that run almost every active jobsite.
Subpart K adopts much of the National Electrical Code (NFPA 70) by reference, but OSHA's construction rules carve out their own, often stricter requirements for temporary wiring. The reason is exposure. A jobsite is a harsher place than a finished building. Wet ground, extension cords dragged through mud, generators feeding three trades at once, and workers focused on framing instead of electrical safety add up to a genuinely different risk picture. [2]
Two other standards run right alongside 1926.405. First, 29 CFR 1926.404 covers ground-fault protection and spells out the GFCI and AEGCP options in detail. Second, 29 CFR 1926.403 sets general requirements for the examination, installation, and use of equipment across all electrical work on a site. Get cited under 1926.405 and the inspector will almost always check 1926.404 in the same walk-around. [1]
For general industry (a manufacturing plant, a warehouse), the parallel standard is 29 CFR 1910.305(a)(2). It does not apply to active construction. Small contractors who do both construction and light manufacturing should know which standard governs which site.
What exactly does OSHA require for temporary wiring on a construction site?
The requirements split into four practical buckets: ground-fault protection, physical protection of conductors, disconnect and overcurrent protection, and inspection and removal. Ground-fault protection is the one inspectors reach for first.
Ground-fault protection. Under 29 CFR 1926.404(b)(1), employers must use one of two approaches on construction sites for all 120-volt, single-phase, 15- and 20-amp receptacle outlets that are not part of the permanent wiring [1]:
- Option 1: Ground-fault circuit interrupter (GFCI) protection on every outlet.
- Option 2: An Assured Equipment Grounding Conductor Program (AEGCP), which requires written procedures, daily visual inspections of cords and equipment, and continuity and polarity testing before first use, after any repair, and at least every three months.
GFCI is simpler for most small contractors. The AEGCP demands a written program, a designated competent person, color-coded inspection dates on every cord and tool, and records of each test. It isn't cheaper in practice unless you run a very large equipment fleet with a dedicated safety person to manage the paperwork.
Physical protection of conductors. Temporary wiring has to be protected from damage. Cables run through doorways, windows, or openings need protection from pinching or abrasion. [1] Cables on the floor in pedestrian or vehicle traffic areas need to be covered, elevated, or otherwise guarded. OSHA doesn't dictate exactly how, but inspectors look for cords sitting where they'll get driven over, buried under debris, or crushed by a closing door.
Extension cords used as temporary wiring must be rated for hard or extra-hard usage (types S, ST, SO, STO, SJ, SJO, SJT, SJTO, and similar designations under NFPA 70). [2] Household-grade cords with two-prong plugs are not acceptable on a construction site, full stop.
Strain relief and connections. Temporary wiring has to be supported and strain-relieved so the weight of the cable doesn't pull on the terminal connections. OSHA's standard points to the NEC requirement that conductors be fastened so tension never reaches the connections. In plain terms: you can't just jam a cord into a panel and let it dangle by the plug.
Overcurrent protection and disconnects. Temporary circuits need overcurrent protection sized to the conductors and a way to disconnect the whole temporary installation. A generator feeding a temporary panel needs a main breaker or a readily accessible disconnect. Circuits can't be tapped in ways that exceed the wiring's rating.
Lamps and lighting. Temporary lighting strings fall under 1926.405(a)(2)(ii)(E). Bulb guards are required unless the fixture itself is built to prevent accidental contact. Lamps can't hang by their cords unless the cord and fixture are rated for it.
Removal. Temporary wiring comes out when the project wraps or when permanent wiring is energized and ready. Leaving temporary wiring live after the permanent system goes hot is a common violation in occupied-space renovations.
How does GFCI protection work and how do you set it up correctly?
A GFCI watches the current difference between the hot and neutral conductors. When that difference tops about 5 milliamps (the trip range varies by device, but UL 943 sets it at 4 to 6 mA), the device cuts power in as little as 1/40th of a second. [3] That's fast enough to prevent cardiac fibrillation in most cases. It will not save you from a painful shock.
For temporary wiring on construction sites, you have three practical ways to get GFCI protection:
1. GFCI circuit breakers installed in the temporary panel or generator distribution panel. These protect everything downstream on that circuit. 2. GFCI receptacles at the outlet. Wire the downstream outlets to the LOAD terminals and they get protection too. Get the LINE/LOAD terminals backward and they don't. 3. Portable GFCI cord sets (the plug-in adapters). These are the most common solution on small sites because they're cheap (roughly $15 to $40 per unit) and need no installation. [3]
Portable GFCI adapters work fine as long as the worker actually uses them and doesn't leave them in the gang box. The real failure mode for small contractors isn't the GFCI, it's the habit around it. Set a site rule: no cord goes into any outlet without a GFCI in the chain, and the adapter stays attached to the cord, never stored separately.
Test your GFCIs. Press TEST, confirm the outlet is dead, press RESET. Do it before each use, or at minimum daily on active sites. A GFCI that doesn't trip on test is defective and has to be replaced. OSHA doesn't mandate a testing frequency for GFCI devices (that mandate belongs to the AEGCP option), but a dead GFCI gives you zero protection, and an inspector who finds one will cite you.
What is an Assured Equipment Grounding Conductor Program and do small contractors need one?
An AEGCP is the written-program alternative to GFCI. Under 29 CFR 1926.404(b)(1)(iii), it must include specific procedures for inspecting and testing equipment, a designated competent person to run the program, and records of every inspection and test. [1]
The testing protocol is specific. Every cord set, attachment cap, plug, receptacle, and extension cord gets a visual inspection before each day's use, looking for damaged insulation, missing ground pins, and broken plugs. Beyond the daily visual, you run continuity testing (the equipment grounding conductor is unbroken) and polarity/proper-termination testing before first use on site, after any repair, and at intervals no longer than three months.
The color-code system: equipment that passes gets a color-coded mark (tape, paint, or a tag) that changes quarterly. The colors are employer-defined, but the scheme has to be documented in the written program. An inspector will ask to see the current color and the program that defines it.
Honest assessment: for a small contractor with a crew of two to five, an AEGCP is almost always more hassle than it's worth. GFCI adapters cost $15 to $40 each, need no paperwork, and actually give better protection (they respond to ground faults even when the grounding conductor is intact). The AEGCP was built for large commercial contractors with hundreds of cords and a full-time safety coordinator. Five-person remodeling crew? Buy GFCI adapters and skip the AEGCP.
The one case where the AEGCP earns its keep is 240-volt or three-phase equipment, where GFCI protection is harder to find and more expensive. For standard 120-volt tools, GFCI wins on simplicity every time.
What are the most common temporary wiring violations OSHA cites on construction sites?
Subpart K (Electrical) shows up in OSHA's top-ten most-cited construction standards year after year. In fiscal year 2023, 1926.405 drew over 1,400 citations and 1926.404 drew over 700, putting electrical fourth among construction groupings behind fall protection, scaffolding, and ladders. [4]
The violations inspectors find most often:
- Missing GFCI protection on 120-volt receptacle circuits. This is the single most common electrical citation on construction sites.
- Extension cords with damaged insulation, missing ground pins, or the wrong type rating (household cords standing in for hard-service cords).
- Temporary wiring left unprotected where it passes through doorways or across vehicle paths.
- Bulb guards missing from temporary lighting.
- Open knockouts or missing covers on temporary panels and junction boxes.
- Conductors spliced without proper connectors (wire nuts on conductors exposed to moisture).
- Temporary wiring left in place after permanent wiring is energized.
The pattern in the enforcement data is simple: citations cluster around what's quickest to spot during a walk-around. Missing GFCIs, damaged cords, open boxes. Those are also the cheapest things to fix. A box of GFCI adapters and a weekly cord inspection would wipe out most temporary wiring citations before an inspector ever pulls up. [4]
Find a serious violation (one where there's a substantial probability that death or serious physical harm could result) and the 2024 penalty runs up to $16,131. Willful or repeat violations reach $161,323. [5] For a small contractor, one serious citation can cost more than a year's worth of GFCI adapters and training combined.
What does OSHA consider a "competent person" for temporary electrical work on a construction site?
OSHA defines a competent person in 29 CFR 1926.32(f) as "one who is capable of identifying existing and predictable hazards in the surroundings or working conditions which are unsanitary, hazardous, or dangerous to employees, and who has authorization to take prompt corrective measures to eliminate them." [11]
For temporary wiring, the competent person requirement lives mainly in the AEGCP context. That person doesn't need an electrician's license, but they do need real knowledge of how to inspect cords, use a continuity tester, spot damaged insulation, and run the color-code tracking.
On non-AEGCP sites using GFCI, OSHA doesn't formally require a designated competent person for the temporary wiring installation itself. But Subpart K still requires electrical work to be done in a "neat and workmanlike manner" and requires equipment to be "approved" (listed or labeled by a nationally recognized testing laboratory). Somebody on your crew has to know enough to set up temporary power correctly. That's not an electrician's license, but it's more than handing a box of extension cords to the newest hire.
If your temporary wiring involves actual panel installation, circuit wiring, or connecting to utility power, you'll almost certainly need a licensed electrician under state licensing law, separate from anything OSHA says. OSHA's competent person standard and state licensing are two different things.
Do OSHA's temporary wiring rules apply to generators on construction sites?
Yes, and this catches small contractors off guard constantly. A portable generator feeding a construction site is supplying temporary power, and everything downstream of it falls under 29 CFR 1926.405 and 1926.404. [1]
The generator itself needs safe placement (exhaust pointed away from any enclosed or semi-enclosed space, because the carbon monoxide risk is real and lethal). The electrical distribution side has to meet the same GFCI and wiring requirements as utility-fed temporary power.
Many small portable generators (the Honda EU series, DeWalt units, and similar) ship with built-in GFCI-protected outlets. Plug directly into those and you're likely covered for 120-volt single-phase circuits. Run a distribution box or "spider box" off the generator, and that box needs GFCI protection on its 120-volt outputs, or every cord plugged into it needs a GFCI adapter at the point of connection.
One trap I see often: a contractor uses a twist-lock to standard-outlet adapter to feed a non-GFCI distribution box from a generator, then runs non-GFCI cords to the tools. That whole chain fails 1926.404. The GFCI protection has to sit at or before the point where the worker touches the circuit.
Carbon monoxide from generators falls under a separate OSHA guidance page on portable generator CO hazards. The electrical side stays entirely inside Subpart K.
How does temporary wiring interact with lockout/tagout requirements on construction sites?
This connection trips up small contractors more than almost anything else in construction electrical safety.
Lockout/tagout under 29 CFR 1910.147 (or the construction-specific energy control provisions) applies when workers service or maintain equipment. If a worker needs to change a blade on a saw plugged into temporary power, unplugging the saw and pocketing the plug is an acceptable form of energy isolation for that tool, because the plug is the lockout device. OSHA's 1910.147 explicitly recognizes plug-and-cord equipment as allowing that simplified isolation. [6]
But if someone needs to work on the temporary panel itself, on the wiring inside it, or on fixed equipment hardwired to temporary wiring, you need a full lockout/tagout procedure. Temporary wiring doesn't lower the lockout bar just because it's temporary.
The confusion comes from treating temporary power as low-risk because it's "just an extension cord." A 20-amp, 120-volt circuit carries enough energy to kill. Any task that opens a junction box, splices a cord under load, or reaches energized components of the temporary distribution system needs energy isolation first.
For more on building a compliant lockout/tagout program, see lockout tagout.
What should a written temporary wiring safety program include for a small contractor?
If you're running the GFCI option (which I recommend for most small contractors), your written program is short. It needs to cover:
1. Scope: which sites and operations the program applies to. 2. GFCI requirement: all 120-volt, 15- and 20-amp receptacle outlets used in construction will have GFCI protection, through breakers, receptacles, or portable adapters. 3. Cord standards: only hard-service or extra-hard-service rated cords (type S, SO, ST, STO, SJ, SJO, SJT, SJTO) will be used. Household cords are prohibited. 4. Daily inspection: workers will visually inspect all cords and GFCI adapters before use. Damaged cords come out of service immediately. 5. GFCI testing: GFCIs will be tested with the TEST/RESET button before first use each day. 6. Physical protection: cords in vehicle or pedestrian paths will be covered or elevated. 7. Removal: temporary wiring will be removed when the project is complete or when permanent wiring is energized and ready. 8. Responsible person: who on the crew owns these items.
Running the AEGCP option instead? The program also needs the written AEGCP procedures, the competent person designation, the color-code system, and the test records.
Writing an electrical safety program from scratch takes real time if you don't already know the standard cold. SafetyFolio's safety program generator produces a site-specific temporary wiring program in about 15 minutes, GFCI or AEGCP sections included, based on your crew size and scope of work.
For the OSHA training requirements that run alongside your written program, see osha training.
What are OSHA penalties for temporary wiring violations and how are they calculated?
OSHA sets maximum penalties by violation category and adjusts them every year for inflation. For 2024, the figures are [5]:
| Violation type | Maximum penalty per violation |
|---|---|
| Other-than-serious | $16,131 |
| Serious | $16,131 |
| Repeat | $161,323 |
| Willful | $161,323 |
| Failure to abate | $16,131 per day |
The penalty a small contractor actually pays usually lands well below the maximum. OSHA runs an adjustment formula that weighs gravity of the violation (probability and severity), good faith (do you have a safety program), history (prior violations), and size. Employers with 25 or fewer employees typically get a 60% reduction; those with 26 to 100 get 40%. [5]
In practice, a first-time serious violation for missing GFCI on a small site might come out to $3,000 to $6,000 after adjustments. Still real money for a crew of four. Repeat violations (same standard, same employer, within five years) lose the size and good-faith reductions and jump toward the $161,000 maximum.
The good-faith credit is the lever you control. A written safety program, documented training, and evidence of regular inspections can cut your penalty by up to 25% even after a violation is confirmed. That alone is reason enough to have the program on paper before an inspection, not after.
How should temporary wiring be inspected on a small construction site?
Inspections don't need to be elaborate. A quick daily walk-around before work starts covers most of what OSHA expects and most of what actually prevents incidents.
What to look for during a daily inspection:
- Every 120-volt receptacle outlet has a GFCI in the circuit. Test it.
- All cords are hard-service rated (check the jacket printing if you're unsure).
- No visible insulation damage: cuts, abrasions, melted spots, or worn areas down to the conductors.
- Ground pins intact on every plug. A missing ground pin means the cord goes in the trash.
- Cords in traffic areas are covered or elevated.
- No cords running through doors or windows where a closing door could chew the jacket.
- Temporary panel covers closed. Open knockouts filled.
- Bulb guards in place on any open-bulb temporary lighting.
- No cords or connections lying in standing water.
Document these inspections. A dated checklist, even on a notepad, is evidence of good faith. Running the AEGCP instead of GFCI? Your documentation load is heavier: you need records of every electrical test, more than visual inspections.
When an incident does happen, knowing how to file an accurate incident report is part of the same compliance picture.
What do state-plan states add to federal OSHA temporary wiring requirements?
Twenty-nine states and territories run their own OSHA-approved state plans. [7] Under federal law, state plans must be "at least as effective" as federal OSHA. They can also be stricter.
For electrical and temporary wiring, most state plans adopt 29 CFR 1926 Subpart K with minimal changes. A few places where states pile on:
- California (Cal/OSHA): Title 8 electrical standards add requirements around temporary power for trenching and excavation work, and Cal/OSHA has historically pushed harder on electrical citations.
- Washington (L&I): WAC 296-155-447 covers construction electrical safety, tracking federal standards but adding some procedural steps around competent person documentation.
- Michigan (MIOSHA): generally tracks federal Subpart K.
The thing that matters most for small contractors in state-plan states: check your state plan's electrical standards before you assume the federal CFR is the whole story. OSHA's site has a state plan directory that links to every state agency. [7]
For a broader look at how state OSHA plans differ from federal requirements, the osha overview covers the structure.
What equipment and supplies do small contractors actually need to stay compliant?
Here's the practical list. None of it is expensive next to the cost of a citation.
Non-negotiable:
- Portable GFCI adapters: one per worker using power tools, plus spares. Budget $15 to $40 each. A 10-pack from an electrical supplier runs $120 to $250.
- Hard-service extension cords (type SJTW or STW for outdoor use): $20 to $60 each depending on length and gauge. A 12-gauge cord carries more load and drops less voltage over distance than a 16-gauge cord. For anything over 50 feet, 12-gauge is worth the extra money.
- Cord reels or storage to keep cords from getting damaged when they're not in use.
- A GFCI outlet tester ($10 to $15): plug it into any outlet to confirm correct wiring and GFCI function. Every crew should carry one.
For temporary panels and distribution:
- A spider box or portable power distribution center with GFCI-protected outlets.
- Weatherproof covers for any outlets that could catch rain.
For AEGCP programs (if you go that route):
- A continuity tester or multimeter ($25 to $80).
- Colored electrical tape or lockout tags for the quarterly color-code system.
- A logbook or simple spreadsheet for test records.
Total spend for a crew of four running GFCI: roughly $300 to $500 to fully equip the site. That's about one-tenth of the minimum likely penalty for a serious GFCI citation.
Frequently asked questions
Does OSHA require a licensed electrician to install temporary wiring on a construction site?
OSHA's 29 CFR 1926 Subpart K does not require a licensed electrician for temporary wiring installation. It requires the work be done by or under the supervision of a qualified or competent person. State electrical licensing laws are separate from OSHA, though, and many states require a licensed electrician for any panel work or circuit installation. Check your state licensing board alongside OSHA.
Can you use household extension cords on a construction site?
No. OSHA's 29 CFR 1926.405 requires extension cords on construction sites to be rated for hard or extra-hard usage, marked with cord type letters such as S, SO, ST, STO, SJ, SJO, SJT, or SJTO. Standard household cords are not acceptable. An inspector finding them on a jobsite will cite you, and they are a genuine shock and fire risk in construction conditions.
How often do GFCI devices need to be tested on a construction site?
OSHA does not set a mandatory testing interval for GFCI devices on sites using the GFCI option (as opposed to the AEGCP). Best practice, reflected in NFPA 70E and most safety programs, is to test with the TEST/RESET button before each use, or at minimum daily. A GFCI that fails to trip on test provides no protection and should be replaced immediately. Testing takes five seconds and costs nothing.
What is the difference between the GFCI option and the AEGCP under 29 CFR 1926.404?
Both satisfy the ground-fault protection requirement for 120-volt, 15- and 20-amp construction site receptacles. GFCI uses listed devices that trip automatically on a fault. The AEGCP (Assured Equipment Grounding Conductor Program) instead requires a written program, a competent person, daily visual inspections, and continuity and polarity testing every three months. GFCI is simpler and the better call for most small contractors. AEGCP mainly earns its keep with large fleets of 240-volt or three-phase equipment.
What happens if OSHA finds temporary wiring violations during an inspection?
OSHA issues a citation with a proposed penalty. Missing GFCI protection on construction sites is typically a serious violation, carrying penalties up to $16,131 per instance in 2024. Small employers (25 or fewer workers) generally receive a 60% size reduction, bringing a typical first citation to roughly $3,000 to $6,000. A written safety program and documented inspections can cut the penalty further through the good-faith credit, up to an additional 25%.
Are temporary wiring rules different for renovation projects inside occupied buildings?
The standard is the same: 29 CFR 1926 Subpart K applies to all construction work, including renovation inside occupied buildings. The practical risk can be higher in occupied spaces because building occupants may touch temporary wiring. One issue specific to renovations: OSHA requires temporary wiring to come out once permanent wiring is energized and ready. Leaving both systems live at the same time is a common violation in phased renovation work.
Do temporary wiring requirements apply to battery-powered tools?
No. The GFCI and temporary wiring requirements under 29 CFR 1926.404 and 1926.405 apply to cord-and-plug connected equipment and receptacle outlets. Battery-powered tools don't plug into temporary power circuits, so those requirements don't reach them. The chargers for battery tools do plug into outlets, though, and they're subject to the same GFCI requirements as any other 120-volt plug-in equipment on the site.
How long can temporary wiring stay in place on a construction project?
OSHA sets no maximum calendar duration for temporary wiring. The requirement is that it be removed when construction is complete or when the permanent wiring is energized and ready for use. A project running 18 months can keep compliant temporary wiring the whole time, as long as it meets every Subpart K requirement. The trigger for removal is project completion or energization of permanent circuits, not elapsed time.
What cord gauge should I use for temporary power on a construction site?
For most 120-volt tools with runs up to 50 feet, 14-gauge cord handles 15-amp circuits and 12-gauge handles 20-amp circuits. Past 50 feet, voltage drop becomes a real problem: 12-gauge is the practical minimum, and 10-gauge is better for 100-foot runs feeding heavy tools like circular saws or compressors. Under-gauge cords overheat, trip breakers, and starve tools of power. The jacket must also suit the environment: type W or outdoor-rated for wet or rough conditions.
Does OSHA's temporary wiring standard apply to self-employed contractors with no employees?
OSHA's jurisdiction generally covers employers with one or more employees. A sole proprietor with zero employees isn't covered by OSHA on their own work. But if that sole proprietor works on a multi-employer construction site, the controlling or general contractor holds responsibility for site-wide electrical safety, and the GC can require subcontractors (including self-employed individuals) to follow OSHA standards as a contract condition. Most GCs do exactly that.
What is a competent person for electrical safety on a construction site?
OSHA's 29 CFR 1926.32(f) defines a competent person as someone capable of identifying existing and predictable hazards and authorized to take corrective action. For temporary wiring, that person needs enough electrical knowledge to inspect cords, test GFCIs, run an AEGCP if applicable, and recognize unsafe conditions. OSHA requires no specific certification, though state licensing laws may add requirements for actual electrical installation work.
Can I use a power strip instead of a proper temporary wiring setup?
No, a power strip is not a substitute for proper temporary wiring on a construction site. Power strips are built for office environments with steady loads, not construction tools drawing high currents. Most aren't rated for hard-usage conditions, lack adequate overcurrent protection for the connected load, and aren't listed for construction use. If you need multiple outlets at a work area, use a listed portable power distribution box or a GFCI-protected multi-outlet assembly rated for the job.
What records do I need to keep for temporary wiring compliance?
For the GFCI option, OSHA mandates no specific records, but a simple daily inspection log is strong evidence of good faith if you ever face a citation. For the AEGCP, records are mandatory: you must document every equipment test (continuity and polarity), the dates, the results, and who ran the test. AEGCP records must be available for inspection. The standard sets no retention period, but keeping records for the project duration plus three years is reasonable.
Sources
- OSHA, 29 CFR 1926 Subpart K (Electrical), federal construction electrical standards: 29 CFR 1926.404(b)(1) requires GFCI or AEGCP protection for 120-volt, single-phase, 15- and 20-amp receptacle outlets on construction sites; 1926.405(a)(2) covers temporary wiring installation requirements
- OSHA, Construction Electrical Safety Overview, OSHA.gov: Construction sites require hard or extra-hard service rated extension cords and adopt much of NFPA 70 by reference for wiring methods
- UL Standards, UL 943 Standard for Ground-Fault Circuit Interrupters: UL 943 sets the GFCI trip threshold at 4 to 6 milliamps, with a portable GFCI cord set costing roughly $15 to $40
- OSHA, Top 10 Most Cited Standards FY2023, OSHA.gov: 29 CFR 1926.405 received over 1,400 citations and 1926.404 received over 700 citations in fiscal year 2023, placing electrical among the most-cited construction standards
- OSHA, Penalties, OSHA.gov: In 2024, maximum OSHA penalties are $16,131 per serious violation and $161,323 per willful or repeat violation; small employers with 25 or fewer workers receive a 60% penalty reduction
- OSHA, 29 CFR 1910.147, The Control of Hazardous Energy (Lockout/Tagout): 29 CFR 1910.147 recognizes plug-and-cord connected equipment as allowing simplified energy isolation by unplugging and retaining the plug
- OSHA, State Plans, OSHA.gov: Twenty-nine states and territories operate their own OSHA-approved state plans that must be at least as effective as federal OSHA standards but may be stricter
- Bureau of Labor Statistics, Census of Fatal Occupational Injuries, BLS.gov: BLS CFOI data tracks fatal electrical injuries in construction; contact with electricity is a leading cause of construction fatalities
- OSHA, 29 CFR 1926.32, Definitions for Construction Standards: OSHA defines competent person under 29 CFR 1926.32(f) as one capable of identifying existing and predictable hazards and authorized to take prompt corrective measures